THE PROJECT

kitchen

The current kitchen is rudimentary and impractical

Planning permission has been gained to improve and upgrade the hall including:

Phase A:

Phase B:

Phase C:


BUILDING PLANS

The pictures below give an aerial view of the proposed extensions, showing which parts are addressed in each phase, and an artist's impression of the new frontage.

aerial view         frontage

To see the architect's outline plans and elevations, click on the links to the right.
(The plans and elevations will open in a pop-up window.)

- Ground floor and Roof plans
- Elevations

lobby

A new entrance lobby and toilets are needed to replace the cramped and outdated space and facilities

THE PROJECT PLAN

Our appeal fund now covers the amount required for phase A and a contract has been let for building phase A, with the option to include Phase B subject to the additional funds being raised. Work started on 28th January 2013 and will take some 30 weeks.

We will continue fund raising and submitting additional grant applications during 2013 to complete the fund raising for phase B. Doing it at the same time as phase A will minimise its cost and the resultant disruption to the hall users. A building plan has been developed which will enable the hall to continue in use for all but a few days throughout the whole construction phase, so minimising revenue loss due to the works.